Pfizer
Mechanical Solutions provided BIM Coordination and HVAC installation for the new 204,000-sq. ft. 3-story office/laboratory building. Equipment installed by Mechanical Solutions included:
69 – variable air volume units with electric reheat
46 – fan powered variable air volume units with electric heat
228 – lab air valves
8 – inline exhaust fans with vibration isolators
27 – fire smoke dampers with access doors
7 – fire dampers with duct access doors as required
97 – ceiling thimbles for point exhaust in labs
97 – bast gates for point exhaust in labs
1,432 – air devices
109 – plaster frames
20 – transfer canopies
20 – transfer ducts with armacell liner
2 – computer room units
13 – chilled water fan coil units with hanger vibration isolators
Project Details
St. Louis, MO
ClientPfizer
Project TypeScience and Technology
ContractorClayco
![Pfizer 3052 scaled 1 Pfizer 3052 scaled 1](https://msi-stl.com/wp-content/uploads/2021/01/Pfizer-3052-scaled-1.jpg)
![Pfizer 3878 Pfizer 3878](https://msi-stl.com/wp-content/uploads/2021/01/Pfizer-3878-scaled.jpg)
![Pfizer 3218 Pfizer 3218](https://msi-stl.com/wp-content/uploads/2021/01/Pfizer-3218-scaled.jpg)
![Pfizer 1 Pfizer 1](https://msi-stl.com/wp-content/uploads/2021/01/Pfizer-1.jpg)
![Pfizer 2 Pfizer 2](https://msi-stl.com/wp-content/uploads/2021/01/Pfizer-2.jpg)
![IMG 9651 edit scaled 2 IMG 9651 edit scaled 2](https://msi-stl.com/wp-content/uploads/2021/01/IMG_9651-edit-scaled-2.jpg)